Network Connection Application Form
IMPORTANT!
Five (5) working days must be allowed to process this application
To be completed by the person accepting responsibility for any costs incurred by this application
Where necessary, this installation must comply with AS/NZS 3000, the current Electricity Regulations, the Network Tasman Distributions Code and must be certified and inspected prior to livening or re-livening
Once this NCA is approved by Network Tasman it is then y our responsibility to arrange a time and date with your nominated Accredited Contractor for Connection, to visit site and complete the works
Easement Route: All necessary electrical easements must be registered prior to NCA approval
This application may incur costs from any of the following: Network Tasman; The nominated Accredited Contractor for Connection; The Energy Retailer; An Auditor; Others. It is your responsibility to determine these costs from the respective companies prior to proceeding with this application
The Electrician should not install the mains cable until the connection point and phasing have been approved by Network Tasman
Network Tasman recommend a meter box size of 600H x 400W x 200D to accommodate a typical meter depth of 115mm
TYPE
Note: Please select one of the following fields
New
- New connection to Network Tasman Distribution system
Metered Builder’s Temporary Supply
- Single phase, 20 amp supply, meter within meter box with 3 pin plug outlet
Metered Builder’s Temporary Supply to Permanent Supply
- change from temporary supply to permanent metered supply
Overhead to Underground Conversion
- Removal of overhead service main and installation of underground supply
Upgrade
- Upgrade capacity/fuse size
Downgrade
- Downgrade capacity/fuse size
Phase Change
- Change the number of phases to an installation
Meter Relocation
- Relocation of meter board position requiring resealing
Reconnection 6 Months +
- Reconnection of Installation (ICP) that has been disconnected > 6 months
Relocate Point of Supply
- Shift Connection Point to Network
Decommission
- Total and permanent removal of metering, fusing and service cable from network
Additional Metering
- Additional metering required
Removal of Some Metering
- Remove some but not all metering
Mains Cable Replacement
- Customer service mains replacement